Friday, June 5, 2009

Week of June the 1st

JUNE 1ST 2009

Bailey Electric is hanging lights on the first floor.

NK Plastering is cleaning and acid washing the brick on the front of the building.

Glen’s Crew is digging the rest of the gutter drain in the front of the building.

Vision Painting is staining the cabinetry that was delivered today.

Carlos is drywalling the iside of the elevator shaft around the doors.

Adam and his crew are building the shelves for the guest room closets

Eddie Ray is prepping the floors for VCT.

Ashley’s crew is setting door frames on the 1st floor and hanging doors on other floors.




JUNE 2ND 2009

Bailey Electric turned power on to the 2nd floor today.

Moses Plumbing is putting in toilets flanges.

Jamell flooring is floating out the floors where the VCT goes. The tile setters are scraping floors.

Better Life Construction is installing soap dishes in the tub units.

NK is cleaning the brick and acid washing the front of the building.

Pioneer Solutions is setting doors on the 2nd floor.

Vision Painting is staining trim.

Glen’s crew is back filling the gutter drains.



JUNE 3RD 2009

Bailey Electric is mounting lights in the gridded ceilings and in the 4th floor corridor.

Moses Mechanical is setting air handlers inside the building.

Carlos is fixing some patch spots in the building.

Burkett paper hanging is hanging paper on the 3rd floor corridor.

Vision Painting is staining trim.

Pioneer Solutions is installing toilet paper holders and tissue boxes in the vanity skirts and hanging doors on the first floor.

Jamell Flooring is prepping floors for VCT.

NK Brick is cleaning the outside of the brick.

Simon Home Improvement is building shelves in closets. Framed the bottom of the laundry chute and extended a mechanical platform.

JUNE 4TH 2009

Bailey Electric is hanging lights in the 3rd floor corridor.

Moses Mechanical is working on the 1st floor air handlers.

Canant Concrete is forming for the side walks and curbs on the front of the buiding.

Vision Painting is staining trim.

Valente is finishing the some patch spots and the walls around the elevator doors.

Pioneer solutions is mounting tissue boxes and toilet paper roll holders.

Jamell Flooring is setting some tile in the Jacuzzi rooms.

Burkett paper hanging is hanging paper on the 2nd and 3rd floor corridor.

June 5, 2009

Bailey Electric is mounting lights in the corridors on 2nd floor.

Canant Concrete is pouring the front porch and sidewalks on the south side of the front of the building.

Burkett Paper Hanging is hanging paper on the 2nd floor corridor.

NK is cleaning the brick.

Moses Mechanical is sweating in the condenser units and measuring for ducts.

Advanced Sprinkler is placing sleeving and putting the cap on the retaining wall.

Diaz block layers are working on the dumpster pad.