Friday, April 24, 2009

4/16 - 4/24

4/16/09 – 4/24/09

Sub contractors on site this week:

Bailey Electric
Moses Mechanical
NK Plastering/brick
Tricon Drywall
Freedom Firepro
Tom January Tile
David Kulp – Granite
Ashley Cox – Door frames

The weather has been very nice this week. Average high in the high 70s. Very little precipitation.


We started hanging sheetrock on the 1st floor Monday. They should be finished hanging by the end of the weekend.

Granite was delivered on Friday the 16th.

David Kulp has been setting and spreading the granite throughout the building all this week.

They started setting door frames last week. The 4th, 3rd and 2nd floor frames are all set other than the closet frames.

Tile was delivered at the end of last week. Tile setters came in Tuesday. They have the 4th and 3rd floor set in the bathrooms and vending areas.

The stub walls were built in rooms 318 and 418 on the 23rd of this month.

90% of the back of the building is bricked and cleaned. The south end of the building is bricked and cleaned. They’re moving scaffolding around to the front of the building.

All of the ptacs and vpacs are set other than two on the first floor.

Wednesday, April 15, 2009

4/15/09

4/15/09

We passed first floor inspection today. G&S is insulating the the walls and ceilings and we'll be loading in rock tomorrow.

Door frames and doors are being installed on the 4th and 3rd floors.

The automatic doors are being installed in the entry way.

The masons are 90% finished with the brick in the back of the building. 30% finished with the sides and have about 6 feet up around the front of the building.

The EIFS is being brown coated on the Porte Corchere.

Glen's crew is spreading dirt and filling in the islands and behind the curbs.

The peirs for the parking light poles have been poured and are ready to have the polse set on them.

The Plumber moved the 1/2" cold water supply for the ice machine to the other side of the dividing wall in the vending areas on the 4th and 3rd floors.