Wednesday, April 15, 2009

4/15/09

4/15/09

We passed first floor inspection today. G&S is insulating the the walls and ceilings and we'll be loading in rock tomorrow.

Door frames and doors are being installed on the 4th and 3rd floors.

The automatic doors are being installed in the entry way.

The masons are 90% finished with the brick in the back of the building. 30% finished with the sides and have about 6 feet up around the front of the building.

The EIFS is being brown coated on the Porte Corchere.

Glen's crew is spreading dirt and filling in the islands and behind the curbs.

The peirs for the parking light poles have been poured and are ready to have the polse set on them.

The Plumber moved the 1/2" cold water supply for the ice machine to the other side of the dividing wall in the vending areas on the 4th and 3rd floors.