The 4th floor is textured and painted and looks very nice. The 3rd floor is textured and all the rooms are painted out. The corridor has to be sanded and primed. Most of the electrical boxes, data boxes and cable TV boxes are trimmed out on those two floors. We're getting ready to seal the bathroom floors and be ready for the tile.

The 2nd floor is being textured right now. It will be painted out next week along with the 3rd floor corridor.

The 1st floor is starting to move along. All of the duct work has been delivered for that floor and is being installed now. The mechanical rooms are being built and misc. framing is going on as well.

The brick will begin this coming week. The EIFS crew is about to finish all they can do for now.

Lighting is being delivered and they're beginning to install those.

The PTACs and VPACs have been delivered and are staged throughout the building.

Our mechanical room has passed inspection and we have our temporary power permit.