Tuesday, October 21, 2008

10-21-08

Weather: Partly cloudy. Highs in the low 70s. 20% chance of rain.


Wilson Bros. is setting the grade in the north parking lot.


Ronnie White (conway building inspector) came out to inspect the perimeter footers. He requested the results of the of the compaction test before we poured concrete. Carl Garner's office faxed over the results and I ran them down to Ronnie's office.


Turner Construction is getting ready to pour concrete in the footers this afternoon.


Garrison is here cleaning out and organizing the connex.


Carl Garner was out on site this morning to look at the issues concerning dry block walls and places where the sub grade is going to be spilling into the drainage ditch. He also looked at the swell that Wilson Bros is putting in the parking lot.


Todd McWilliams came by to pick up his contract.


Brett, Kerry's digger, is on site to redig the footers that have been reengineered to accommodate the pool a whirl pool.


David Wingfield came the site to look at the plans and put together a bid proposal for this job.



Brundage Bone sent a pumper truck out and Keryy poured about 90% of the outside peremiter.


Wilson Bros. started spreading gravel on the north end of the parking lot.