Monday, October 20, 2008

Weather: Mostly sunny. Highs in the mid 70s. 20% chance of rain.

Wilson Bros. arrived on site around 7 am and started working on the grade at the north end of the parking lot.


Turner construction arrived on site about 7 am and started cleaning out the rooters and setting in the steel.


Moses Plumbing came by to hook up the water to the office and connect the bladder.


We went to Home Depot to get a pump, but we had to put it back because the card number we had wasn't valid unless swiped.


Freedom Fire came out to pressurize the supply line.


Julie with the pump truck company came out to discuss where to stage the pumper.


We got some supplies to organize the office and worked on that some of the afternoon.


Conway corp. came and approved out water RPZ for the office and our temporary bladder/tank. We now have water in the office trailer.


United Rental brought a Whacker Packer out for Kerry to clean up the footers.


Kerry called in for a footer inspection for the morning.