Turner Construction is here setting some forms in the northg parking lot and doing some misc. clean up.


Todd with Advanced Sprinkler is moving some of the dirt spoils off of the site.


JR with Bailey Electric is on site doing some feild checks.


Joey and Alan were in town today to meet with the Patels. They made the decision to enlarfe the whirlpool.


Southland is framing the second floor. One of the lift operators drove the sky track around the back of the building and blew part of the dry block wall out. They stood most of the exterior walls up and put down extra OSB in the corridor.


12/9/08


Weather: Raining and cloudy. Nearly half an inch of rain fell over night. The site is ver wet and muddy. Chances of rain all day and into the night.


Southalnd is here framing the 2nd floor. They will be read for trusses tomorrow. There have been several issues worked out between Southland and Chase about deminsions in several of the bathrooms.


Ron with Seaside Pools came out to see what needs to be done about expanding the whirlpool.


We recieved the shop drawings for the linen chute that the office had send over.