Trusses for the roof were delivered to the site on 12/30/08 and 12/31/08. The trusses delivered on the 30th were loaded very poorly. One bundle had a metal band strapped to the bundle below it and it broke a top cord. Southland framers worked over the weekend setting the trusses.
1/05/09
Weather: Cold and wet. 100% chance of rain, freezing rain and sleet. Highs in the mid 30s and falling throughout the day.
The 3rd and 4th floor have been icing over and getting dangerous.
Part of Southalnds framing crew was here this morning. Alex got here around noon and Oswaldo was about an hour behind him. The framers started rolling up about 3pm
Bailey's crew has been running home runs and putting temp lights up in the 3rd floor.
Moses Mechanical didn't get here until around noon because of the weather.
Moses Plumbing was here this morning and working all day.
Seaside pools showed up about noon and started working on the whirl pool.
1/6-7/09
Moses Mechanical and Plumbing have been here working. Plumbing is taking their plastic up. They have called in for an above ceiling inspection for the 1st floor. Mechanical is running sheet metal duct for exhaust fans.
Bailey is setting boxes and running home runs where they can. They're fire caulking in the first floor for everything below 8 ft.
Southland is setting piggy back trusses and building the stair case in the lobby.