JUNE 1ST 2009
Bailey Electric is hanging lights on the first floor.
NK Plastering is cleaning and acid washing the brick on the front of the building.
Glen’s Crew is digging the rest of the gutter drain in the front of the building.
Vision Painting is staining the cabinetry that was delivered today.
Carlos is drywalling the iside of the elevator shaft around the doors.
Adam and his crew are building the shelves for the guest room closets
Eddie Ray is prepping the floors for VCT.
Ashley’s crew is setting door frames on the 1st floor and hanging doors on other floors.
JUNE 2ND 2009
Bailey Electric turned power on to the 2nd floor today.
Moses Plumbing is putting in toilets flanges.
Jamell flooring is floating out the floors where the VCT goes. The tile setters are scraping floors.
Better Life Construction is installing soap dishes in the tub units.
NK is cleaning the brick and acid washing the front of the building.
Pioneer Solutions is setting doors on the 2nd floor.
Vision Painting is staining trim.
Glen’s crew is back filling the gutter drains.
JUNE 3RD 2009
Bailey Electric is mounting lights in the gridded ceilings and in the 4th floor corridor.
Moses Mechanical is setting air handlers inside the building.
Carlos is fixing some patch spots in the building.
Burkett paper hanging is hanging paper on the 3rd floor corridor.
Vision Painting is staining trim.
Pioneer Solutions is installing toilet paper holders and tissue boxes in the vanity skirts and hanging doors on the first floor.
Jamell Flooring is prepping floors for VCT.
NK Brick is cleaning the outside of the brick.
Simon Home Improvement is building shelves in closets. Framed the bottom of the laundry chute and extended a mechanical platform.
JUNE 4TH 2009
Bailey Electric is hanging lights in the 3rd floor corridor.
Moses Mechanical is working on the 1st floor air handlers.
Canant Concrete is forming for the side walks and curbs on the front of the buiding.
Vision Painting is staining trim.
Valente is finishing the some patch spots and the walls around the elevator doors.
Pioneer solutions is mounting tissue boxes and toilet paper roll holders.
Jamell Flooring is setting some tile in the Jacuzzi rooms.
Burkett paper hanging is hanging paper on the 2nd and 3rd floor corridor.
June 5, 2009
Bailey Electric is mounting lights in the corridors on 2nd floor.
Canant Concrete is pouring the front porch and sidewalks on the south side of the front of the building.
Burkett Paper Hanging is hanging paper on the 2nd floor corridor.
NK is cleaning the brick.
Moses Mechanical is sweating in the condenser units and measuring for ducts.
Advanced Sprinkler is placing sleeving and putting the cap on the retaining wall.
Diaz block layers are working on the dumpster pad.
Friday, June 5, 2009
Friday, April 24, 2009
4/16 - 4/24
4/16/09 – 4/24/09
Sub contractors on site this week:
Bailey Electric
Moses Mechanical
NK Plastering/brick
Tricon Drywall
Freedom Firepro
Tom January Tile
David Kulp – Granite
Ashley Cox – Door frames
The weather has been very nice this week. Average high in the high 70s. Very little precipitation.
We started hanging sheetrock on the 1st floor Monday. They should be finished hanging by the end of the weekend.
Granite was delivered on Friday the 16th.
David Kulp has been setting and spreading the granite throughout the building all this week.
They started setting door frames last week. The 4th, 3rd and 2nd floor frames are all set other than the closet frames.
Tile was delivered at the end of last week. Tile setters came in Tuesday. They have the 4th and 3rd floor set in the bathrooms and vending areas.
The stub walls were built in rooms 318 and 418 on the 23rd of this month.
90% of the back of the building is bricked and cleaned. The south end of the building is bricked and cleaned. They’re moving scaffolding around to the front of the building.
All of the ptacs and vpacs are set other than two on the first floor.
Sub contractors on site this week:
Bailey Electric
Moses Mechanical
NK Plastering/brick
Tricon Drywall
Freedom Firepro
Tom January Tile
David Kulp – Granite
Ashley Cox – Door frames
The weather has been very nice this week. Average high in the high 70s. Very little precipitation.
We started hanging sheetrock on the 1st floor Monday. They should be finished hanging by the end of the weekend.
Granite was delivered on Friday the 16th.
David Kulp has been setting and spreading the granite throughout the building all this week.
They started setting door frames last week. The 4th, 3rd and 2nd floor frames are all set other than the closet frames.
Tile was delivered at the end of last week. Tile setters came in Tuesday. They have the 4th and 3rd floor set in the bathrooms and vending areas.
The stub walls were built in rooms 318 and 418 on the 23rd of this month.
90% of the back of the building is bricked and cleaned. The south end of the building is bricked and cleaned. They’re moving scaffolding around to the front of the building.
All of the ptacs and vpacs are set other than two on the first floor.
Wednesday, April 15, 2009
4/15/09
4/15/09
We passed first floor inspection today. G&S is insulating the the walls and ceilings and we'll be loading in rock tomorrow.
Door frames and doors are being installed on the 4th and 3rd floors.
The automatic doors are being installed in the entry way.
The masons are 90% finished with the brick in the back of the building. 30% finished with the sides and have about 6 feet up around the front of the building.
The EIFS is being brown coated on the Porte Corchere.
Glen's crew is spreading dirt and filling in the islands and behind the curbs.
The peirs for the parking light poles have been poured and are ready to have the polse set on them.
The Plumber moved the 1/2" cold water supply for the ice machine to the other side of the dividing wall in the vending areas on the 4th and 3rd floors.
We passed first floor inspection today. G&S is insulating the the walls and ceilings and we'll be loading in rock tomorrow.
Door frames and doors are being installed on the 4th and 3rd floors.
The automatic doors are being installed in the entry way.
The masons are 90% finished with the brick in the back of the building. 30% finished with the sides and have about 6 feet up around the front of the building.
The EIFS is being brown coated on the Porte Corchere.
Glen's crew is spreading dirt and filling in the islands and behind the curbs.
The peirs for the parking light poles have been poured and are ready to have the polse set on them.
The Plumber moved the 1/2" cold water supply for the ice machine to the other side of the dividing wall in the vending areas on the 4th and 3rd floors.
Friday, March 27, 2009
3/27/09
The 4th floor is textured and painted and looks very nice. The 3rd floor is textured and all the rooms are painted out. The corridor has to be sanded and primed. Most of the electrical boxes, data boxes and cable TV boxes are trimmed out on those two floors. We're getting ready to seal the bathroom floors and be ready for the tile.
The 2nd floor is being textured right now. It will be painted out next week along with the 3rd floor corridor.
The 1st floor is starting to move along. All of the duct work has been delivered for that floor and is being installed now. The mechanical rooms are being built and misc. framing is going on as well.
The brick will begin this coming week. The EIFS crew is about to finish all they can do for now.
Lighting is being delivered and they're beginning to install those.
The PTACs and VPACs have been delivered and are staged throughout the building.
Our mechanical room has passed inspection and we have our temporary power permit.
The 2nd floor is being textured right now. It will be painted out next week along with the 3rd floor corridor.
The 1st floor is starting to move along. All of the duct work has been delivered for that floor and is being installed now. The mechanical rooms are being built and misc. framing is going on as well.
The brick will begin this coming week. The EIFS crew is about to finish all they can do for now.
Lighting is being delivered and they're beginning to install those.
The PTACs and VPACs have been delivered and are staged throughout the building.
Our mechanical room has passed inspection and we have our temporary power permit.
Friday, February 27, 2009
2/12/09-2/26/09
2/12
Weather: Partly cloudy. Highs in the low 60s. 10% chance of rain.
Sub List:
Bailey Electric
Moses Plumbing
Moses Mechanical
Advanced Cable
Tricon Drywall
Southland Framing
NK Plastering
Trikon has drywall in all of the guest rooms on the 4th floor. They are putting up channel in the corridor.
All of the MEPs have finished with the 3rd floor. The inspector has been called in for tomorrow.
NK Plastering is mudding screw holes on the north and south ends of the building.
2/13
Weather: Mostly cloudy. Highs in the low 60s. 60% chance for rain in the afternoon.
Sub List:
Bailey Electric
Moses Plumbing
Moses Mechanical
Advanced Cable
Tricon Drywall
Southland Framing
NK Plastering
Our inspection was delayed due to Bailey. They ran out of fire putty for their boxes and they couldn't find anymore in the state.
Tricon is putting drywall on the 4th floor corridor.
Southland is working on the Porte Corchere and the fur downs in the second floor corridor
NK Plastering is mud coating the north and south ends of the building.
2/16
Weather: Mostly clear. Highs in the low 60s. 10% chance of rain.
Sub List:
Bailey Electric
Moses Mechanical
Moses Plumbing
Tricon Drywall
Southland Framing
NK Plastering
Freedom Firepro
It's President's Day, so the city offices in Conway are closed. We won't be able to get the 3rd floor inspected until tomorrow.
Freedom Fire has put 200 lbs of pressure on the 2nd, 3rd and 4th floors and they all held fine. They will come back for the first floor in a couple of days.
Moses Mechanical is on the 2nd floor running duct for exhaust fans and hear and air for the corridor.
Moses Plumbing is setting tub valves on the 2nd floor and getting ready to set tubs.
Bailey Electric is puttying all their boxes on the 3rd floor.
NK Plastering is finished putting color on the north side of the building. They are taking down their scaffolding.
Southland is putting in blocking on the 4th floor and working on the porte corchere.
Greg with Custom Glass came by with the fellow from the automatic door company to get measurements on the store front doors. Greg had told us to just frame the opening at whatever width and they would have the door built to that size. Today they told Alex that he needed to have 5' of clearance for the doors. So he will have to make some adjustments.
2/17
Weather: Partly cloudy. Highs near 50. 30% chance of rain and thunderstorms over night.
Sub List:
Bailey Electric
Moses Mechanical
Moses Plumbing
Southland Framing
Tricon Drywall
NK Plastering
Southland is workinf on the Porte Corchere in the front of the building. There were a few VTAC closets on the 2nd floor that were framed wrong. Alex got them to change them around to the right spot. The got in fixed in no time.
NK Plastering is finishing up on the south end of the building. They still have the dormers to do. The north end of the building is finished.
We couldn't get the inspectors out here today. It'll be tomorrow before they can make it out.
Tricon is cleaning up their trash on the 4th floor.
Bailey is putting putty on their boxes on the 3rd floor.
Adam with Simon Home Improvement is here with a couple of guys to put the exterior metal doors in.
Moses Plumbing is setting tubs on the 2nd floor and getting ready to drop down to the 1st floor.
Gypsom was delvered for the gypcrete company. I unloaded 9 skids of gypsom out back.
Weather: Mostly clear. Highs in the upper 60s.
Sub List:
Bailey Electric
Moses Plumbing
Moses Mechanical
Southland Framing
Tricon Drywall
G and S insulation
NK Plastering
Advanced Cable
Advanced Sprinkler
Paul Young, Conway building inspector, came by to look at the 3rd floor. We had some draft stop issues and a little bit of pre rock and fire tape that needed to take place at the ends of the corridor. He said to take care of that and go ahead and insulate and he would reinspect tomorrow.
Tricon Drywall took care of the pre rock and fire tape issues.
I had my guys take care of the draft stop issues.
Southland Framing is working on the Porte Corchere and the front porch. They got the rafters hung for the porch.
GS Insulation worked late and insulated the whole 3rd floor.
Todd came over to move some loads of sand that someone had dumped right in out way.
Moses Plumbing is running copper down from the 2nd floor
Moses Mechanical is running duct work on the 2nd floor.
I spent all day working numbers and openings for the granite tops.
2/19
Weather: Mostly clear and cool. Highs around 40.
sub List:
Bailey Electric
Moses Mechanical
Moses Plumbing
Southland Framing
Tricon Drywall
Advanced Cable
NK Plastering
Tricon Drywall got all the ceilings in the guest rooms on the 3rd floor. The tapers have started on the 4th floor.
Southland is working on the porte corchere and front porch.
Bailey is puttin putty on their boxes on the 2nd floor and fire caulking their penatrations.
Moses Plumbing is setting everything on the 2nd floor. They're setting tubs and tub valves
Moses Mechanical is running ducts down the 2nd floor corridor and fixing the ducts that Ronnie said was wrong.
Ronnie White came by this morning to reinspect the 3rd floor. He said that the flex duct that Moses had in the corridor wasn't going to work.
NK Plastering finished the EIFS on the south side.
2/23
Weather: Mostly clear. Highs around 50.
Conway Corp came out and set up out RPZ and meter on the fire hydrant for Advanced Surfaces.
We ordered some more sheets of drywall (5/8" by 4x10) plus screws and nails.
John got with the brick guys about staging their material and gave them a copy of the elevation and plan.
The EIFS should finish with the back of the building this week and be ready to do the dormers.
John met with all the MEP supers this morning to discuss the 2nd and 1st floors.
Kevin was off site today.
2/24
Weather: Partly Cloudy. Highs in the 50s. 10% chance of rain.
Sub List:
Bailey Electric
Moses Mechanical
Moses Plumbing
Southland Framing
Tricon Drywall
Advanced Sprinkler
Seize Signs
Bailey is finishing the 2nd floor and moving down to the 1st.
Moses Mechanical is on the second floor getting ready to run exhaust down to the 1st floor.
Moses Plumbing is finishing up the copper on the 2nd floor.
Todd came by and dug the hole for the sign company.
Cody with Seize signs came and met with Todd and Jerime about the pylon sign.
Tricon Drywall is hanging on the 3rd floor and prerocking in the 2nd floor.
Southland is working on the Fron porch and entry way.
2/25
Weather: Partly cloudy, highs in the 60s
Sub List:
Bailey Electric
Moses Plumbing
Moses Mechanical
Southland Framing
Tricon Drywall
Seize Sign
Advanced Surfaces
Roofers
Bailey isi down on the 1st floor finishing their rough in and fire caulking penetrations. They're running conduit to the porte corchere to supply it with power.
Moses Mechanical is fire caulking their condecsate lines and thermostat wire that penetrate the top and bottom plates.
Moses Plumbing is setting the tubs and tub valves on the 2nd floor.
Southland framing is working on the front entry door and tyvecking the porte corchere.
Tricon Drywall is hanging the 3rd floor and getting ready for gypcrete on the 4th.
Advanced Surfaces set up their equipment in the back of the building and ran hoses up to the 4th floor.
Seize Signs set rebar and put together the anchor bolts for the pylon sign. I unloaded the poles off of the truck for them.
Jon Wilsie and his roofing crew came and put the EPDM on the flat roof areas.
2/26
Weather: Mostly Cloudy. Highs in the 60s. Chance of rain in the evening.
Sub List:
Bailey Electric
Moses Plumbing
Moses Mechanical
Tricon Drywall
Southland Framing
Advanced Surfaces
Seize Signs
Elite roofing
Bailey is on the 1st floor.
Ronnie White came to inspect the 2nd floor. There were some draft stop issues and fire tape issues. He'll be back Monday.
Moses Mechanical is on the 1st floor running ducts.
Moses Plumbing is running 1st floor up to the 2nd floor. They had a few penetrations to fire caulk in the laundry room and corridor.
Southland crew is working on fur downs and the front door. Alex got Osvaldo and his guys to help clean up and patch holes on the 3rd floor in front of the gypcrete guys.
Tricon Drywall is cleaing the 3rd floor of trash and sheetrock debri. They moved out an enormous pile of trash and got the floor clean in time for the gypcrete.
Advanced Surfaces poured gyp on the 4th and half of the 3rd floor today.
Weather: Partly cloudy. Highs in the low 60s. 10% chance of rain.
Sub List:
Bailey Electric
Moses Plumbing
Moses Mechanical
Advanced Cable
Tricon Drywall
Southland Framing
NK Plastering
Trikon has drywall in all of the guest rooms on the 4th floor. They are putting up channel in the corridor.
All of the MEPs have finished with the 3rd floor. The inspector has been called in for tomorrow.
NK Plastering is mudding screw holes on the north and south ends of the building.
2/13
Weather: Mostly cloudy. Highs in the low 60s. 60% chance for rain in the afternoon.
Sub List:
Bailey Electric
Moses Plumbing
Moses Mechanical
Advanced Cable
Tricon Drywall
Southland Framing
NK Plastering
Our inspection was delayed due to Bailey. They ran out of fire putty for their boxes and they couldn't find anymore in the state.
Tricon is putting drywall on the 4th floor corridor.
Southland is working on the Porte Corchere and the fur downs in the second floor corridor
NK Plastering is mud coating the north and south ends of the building.
2/16
Weather: Mostly clear. Highs in the low 60s. 10% chance of rain.
Sub List:
Bailey Electric
Moses Mechanical
Moses Plumbing
Tricon Drywall
Southland Framing
NK Plastering
Freedom Firepro
It's President's Day, so the city offices in Conway are closed. We won't be able to get the 3rd floor inspected until tomorrow.
Freedom Fire has put 200 lbs of pressure on the 2nd, 3rd and 4th floors and they all held fine. They will come back for the first floor in a couple of days.
Moses Mechanical is on the 2nd floor running duct for exhaust fans and hear and air for the corridor.
Moses Plumbing is setting tub valves on the 2nd floor and getting ready to set tubs.
Bailey Electric is puttying all their boxes on the 3rd floor.
NK Plastering is finished putting color on the north side of the building. They are taking down their scaffolding.
Southland is putting in blocking on the 4th floor and working on the porte corchere.
Greg with Custom Glass came by with the fellow from the automatic door company to get measurements on the store front doors. Greg had told us to just frame the opening at whatever width and they would have the door built to that size. Today they told Alex that he needed to have 5' of clearance for the doors. So he will have to make some adjustments.
2/17
Weather: Partly cloudy. Highs near 50. 30% chance of rain and thunderstorms over night.
Sub List:
Bailey Electric
Moses Mechanical
Moses Plumbing
Southland Framing
Tricon Drywall
NK Plastering
Southland is workinf on the Porte Corchere in the front of the building. There were a few VTAC closets on the 2nd floor that were framed wrong. Alex got them to change them around to the right spot. The got in fixed in no time.
NK Plastering is finishing up on the south end of the building. They still have the dormers to do. The north end of the building is finished.
We couldn't get the inspectors out here today. It'll be tomorrow before they can make it out.
Tricon is cleaning up their trash on the 4th floor.
Bailey is putting putty on their boxes on the 3rd floor.
Adam with Simon Home Improvement is here with a couple of guys to put the exterior metal doors in.
Moses Plumbing is setting tubs on the 2nd floor and getting ready to drop down to the 1st floor.
Gypsom was delvered for the gypcrete company. I unloaded 9 skids of gypsom out back.
Weather: Mostly clear. Highs in the upper 60s.
Sub List:
Bailey Electric
Moses Plumbing
Moses Mechanical
Southland Framing
Tricon Drywall
G and S insulation
NK Plastering
Advanced Cable
Advanced Sprinkler
Paul Young, Conway building inspector, came by to look at the 3rd floor. We had some draft stop issues and a little bit of pre rock and fire tape that needed to take place at the ends of the corridor. He said to take care of that and go ahead and insulate and he would reinspect tomorrow.
Tricon Drywall took care of the pre rock and fire tape issues.
I had my guys take care of the draft stop issues.
Southland Framing is working on the Porte Corchere and the front porch. They got the rafters hung for the porch.
GS Insulation worked late and insulated the whole 3rd floor.
Todd came over to move some loads of sand that someone had dumped right in out way.
Moses Plumbing is running copper down from the 2nd floor
Moses Mechanical is running duct work on the 2nd floor.
I spent all day working numbers and openings for the granite tops.
2/19
Weather: Mostly clear and cool. Highs around 40.
sub List:
Bailey Electric
Moses Mechanical
Moses Plumbing
Southland Framing
Tricon Drywall
Advanced Cable
NK Plastering
Tricon Drywall got all the ceilings in the guest rooms on the 3rd floor. The tapers have started on the 4th floor.
Southland is working on the porte corchere and front porch.
Bailey is puttin putty on their boxes on the 2nd floor and fire caulking their penatrations.
Moses Plumbing is setting everything on the 2nd floor. They're setting tubs and tub valves
Moses Mechanical is running ducts down the 2nd floor corridor and fixing the ducts that Ronnie said was wrong.
Ronnie White came by this morning to reinspect the 3rd floor. He said that the flex duct that Moses had in the corridor wasn't going to work.
NK Plastering finished the EIFS on the south side.
2/23
Weather: Mostly clear. Highs around 50.
Conway Corp came out and set up out RPZ and meter on the fire hydrant for Advanced Surfaces.
We ordered some more sheets of drywall (5/8" by 4x10) plus screws and nails.
John got with the brick guys about staging their material and gave them a copy of the elevation and plan.
The EIFS should finish with the back of the building this week and be ready to do the dormers.
John met with all the MEP supers this morning to discuss the 2nd and 1st floors.
Kevin was off site today.
2/24
Weather: Partly Cloudy. Highs in the 50s. 10% chance of rain.
Sub List:
Bailey Electric
Moses Mechanical
Moses Plumbing
Southland Framing
Tricon Drywall
Advanced Sprinkler
Seize Signs
Bailey is finishing the 2nd floor and moving down to the 1st.
Moses Mechanical is on the second floor getting ready to run exhaust down to the 1st floor.
Moses Plumbing is finishing up the copper on the 2nd floor.
Todd came by and dug the hole for the sign company.
Cody with Seize signs came and met with Todd and Jerime about the pylon sign.
Tricon Drywall is hanging on the 3rd floor and prerocking in the 2nd floor.
Southland is working on the Fron porch and entry way.
2/25
Weather: Partly cloudy, highs in the 60s
Sub List:
Bailey Electric
Moses Plumbing
Moses Mechanical
Southland Framing
Tricon Drywall
Seize Sign
Advanced Surfaces
Roofers
Bailey isi down on the 1st floor finishing their rough in and fire caulking penetrations. They're running conduit to the porte corchere to supply it with power.
Moses Mechanical is fire caulking their condecsate lines and thermostat wire that penetrate the top and bottom plates.
Moses Plumbing is setting the tubs and tub valves on the 2nd floor.
Southland framing is working on the front entry door and tyvecking the porte corchere.
Tricon Drywall is hanging the 3rd floor and getting ready for gypcrete on the 4th.
Advanced Surfaces set up their equipment in the back of the building and ran hoses up to the 4th floor.
Seize Signs set rebar and put together the anchor bolts for the pylon sign. I unloaded the poles off of the truck for them.
Jon Wilsie and his roofing crew came and put the EPDM on the flat roof areas.
2/26
Weather: Mostly Cloudy. Highs in the 60s. Chance of rain in the evening.
Sub List:
Bailey Electric
Moses Plumbing
Moses Mechanical
Tricon Drywall
Southland Framing
Advanced Surfaces
Seize Signs
Elite roofing
Bailey is on the 1st floor.
Ronnie White came to inspect the 2nd floor. There were some draft stop issues and fire tape issues. He'll be back Monday.
Moses Mechanical is on the 1st floor running ducts.
Moses Plumbing is running 1st floor up to the 2nd floor. They had a few penetrations to fire caulk in the laundry room and corridor.
Southland crew is working on fur downs and the front door. Alex got Osvaldo and his guys to help clean up and patch holes on the 3rd floor in front of the gypcrete guys.
Tricon Drywall is cleaing the 3rd floor of trash and sheetrock debri. They moved out an enormous pile of trash and got the floor clean in time for the gypcrete.
Advanced Surfaces poured gyp on the 4th and half of the 3rd floor today.
Tuesday, February 10, 2009
2/5 - 2/7
![]() |
| From Job # 8.02 / CIS |
2-5-09
Weather: Mostly clear. Highs around 50
Sub List:
Bailey Electric
Moses Plumbing
Moses Mechanical
Southland Framing
NK Plastering
Freedom Firepro
Freedom Fire is fire caulking their penatractions on the 4th floor. They're finishing their work in the attic.
Bailey is having to fire caulk behind the data and ire alarm crews becuase they couldn't get it done in time for inspection.
Moses Mechanical is installing the fire dampers in the attic.
Mike Cordiss sent most of his crew over to mechanical to help them catch up on their work.
2-06-09
Weather: Mostly clear. Highs around 50
Sub List:
Bailey Electric
Moses Mechanical
Moses Plumbing
Southland Framing
Ron White, Conway building inspector, came and reinspected the 4th floor. He said we have to build cat walks to both exhaust units in the attic. we also have to pour light weight concrete in the exhaust duct chases in the closet.
Moses Plumbing left for home right after the inspection
Southland Framing started on the Porte Corche. They added a 2x6 on a slight slope at the top to give the roof a little pitch.
Moses Mechanical dropped down to the 3rd floor to work on their ducts.
2-9-09
Weather: Cloudy and raining. Hights around the mid 50s.
Sub List:
Bailey Electric
Moses Plumbing
Moses Mechanical
NK Plastering
G&S Inulation
Souhtland Framing
Freedom Firepro
Tricon Drywall
All the MEPs are down on the 3rd floor getting ready for the inspection later this week. We're waiting on Chase to give us details about the corridors ceilings on the 1st, 2nd and 3rd floors.
Southland framers are working on the Porte Corche and front porch.
G&S Insulation is insulating the 4th floor walls. They didn't get it all done today. I've scheduled them to come back on Saturday the 14th to insulate the 3rd floor.
Tricon is rocking the ceilings on the 4th floor except for the ceilings that we have to leave open per Ron White, Conway building inspector.
Freedome Fire is putting caps on the ends of all their suppresion lines so that they can run an air pressure test.
Thursday, February 5, 2009
1/28/09 - 2/4/09
1/28/09
Weather: cold and mostly cloudy. Highs around the low 30s. Still dealing with some icy spots.
Sub List:
Bailey Electric
Moses Plumbing
Moses Mechanical
Southland Framing
Bailey is marking spots for corridor lights and putting putty on their boxes.
Moses Mechanical is putting together ducts and installing them in the chases in the suites.
Moses Plumbing is getting everything ready to set tubs and tub valves.
Southland framers came on site around 3:30 pm
1/29/09
Weather: Cold and mostly cloudy. Average temperature in the low 30s.
Sub List:
Bailey Electric
Moses Mechanical
Moses Plumbing
NK Plastering
Southland Framing
Tricon Drywall
Freedom Firepro
Bailey Electric is putting boxes on the 4th floor and wrapping up little incidentals for inspection. Jerime installed the MDP in the mechanical room on the 1st floor.
Moses Plumbing is setting tubs and tub valves and drains and fire caulking all their penetrations on the 4th floor.
Moses Mechanical is setting PTAC sleeves on the 4th floor. They're running duct in the attic for exhaust etc.
Freedom Firepro was here for a little while this morning, but went home because it was too cold to glue pipe.
NK Plastering is mudding over holes and screw heads.
Advanced Wireless is running cable to boxes on the 4th floor.
Southland framing is building fur outs around the exhaust fan duct work in the closets. They're framing the rest of the chase around the VTAC ducts on the 4th floor. They're putting in stair well blocking and hold downs in the sheer walls.
Tricon Drywall is fixing a spot in the 4th floor corridor where there was only one layer of 5/8s rock. They're putting RC channel on the ceiling of the rooms on the 4th floor.
1/30/09
Weather: Mostly cloudy. Highs in the low 50s. Cold this morning and muddy on site.
Sub List:
Bailey Electric
Moses Plumbing
Moses Mechanical
Southland Framing
Tricon Drywall
NK Plastering
Freedom Firepro
Advanced Wireless (data)
Bailey is pulling wires to their Main Distribution Panel (MDP) in the 1st floor mechanical room
Moses Plumbing is finishing the tubs on the 4th floor. They're setting drains and copper.
Moses mechanical is setting PTAC sleeves and readjusting some for the new brick/EIFS design for the exterior.
NK Plastering is spreading mesh and mud on the west side of the building.
I moved Tricon down to the 3rd floor to give the plumbers more space to work on the 4th. They're putting RC channel on the ceilings of the rooms.
Our MEP inspection has been moved to Monday.
John left at 11 am to go to Ft. Smith for a meeting.
I got Magnum Materials to fax over all the invoices for the this job.
2/2/09
Weather: Mostly clear. Highs near 50.
Sub List:
Bailey Electric
Moses Plumbing
Moses Mechanical
Canant Construction
NK Plastering
Advanced Wireless
Canant Construction is pouring concrete in the north parking lot this morning.
Moses Plumbing has their tubs and tub valves in place and they are ready for inspection.
Moses mechanical still has some work to do up in the attic with their duct work. They still have some drains or condensation lines on the 4th floor.
Bailey is ready for inspection on the 4th floor. They are running wires back to the MDP on the 1st.
NK Plastering is spreading color on the front of the building.
The owners and Chase met with John in the office.
2/3/09
Sub List:
Bailey Electric
Moses Plumbing
Moses Mechanical
Southland Framing
NK Plastering
Canant Construction
Tricon Drywall
We had our 4th floor MEP and framing inspection first thing this morning. There were some HVAC and fire suppression issues in the attic and some fire caulking issues with the low voltage and fire alarm people and Freedom Firepro that kep us from passing. Steps are being taken to remedy those problems. Electrical, Plumbing and Framing didn't have any issues.
Bailey is down on 3rd floor joining boxes and pulling wire.
Moses Plumbing is setting tubs on the 3rd floor and getting ready to set tub valves.
Moses Mechanical is finishing their duct work in the attic and putting in the vent for the laundry chute. Elite roofing came today to change out the roof curbs for Moses. Moses' guys dropped their pipe through and capped the curbs.
Canant Construction saw cut the parking lot today.
Tricon Drywall came in and rocked the top of the closets where the exhaust ducts run. They're putting RC channel on the 3rd floor ceilings.
Southland has a few guys here doing 4th floor punch and clean up.
2/4/09
Weather: Mostly clear. Highs in the mid 40s.
Sub List:
Bailey Electric
Moses Plumbing
Moses Mechanical
NK Plastering
Tricon Drywall
Southland Framing
Freedom Firepro.
Bailey is working on the 3rd floor getting ready for 3rd floor inspection next week.
Moses Plumbing is getting the 3rd floor ready for inspection.
John had to leave around 9:30 for a meeting in Searcy. He didn't get back until around 4.
NK Plastering has put the color and window trim on the front section of the building and a lot of the back of the building. They started taking down scaffolding this afternoon.
Southland is cleaning up all the materials off of the 4th floor.
The trusses for the front porch and Porte Corche were delivered this morning.
Weather: cold and mostly cloudy. Highs around the low 30s. Still dealing with some icy spots.
Sub List:
Bailey Electric
Moses Plumbing
Moses Mechanical
Southland Framing
Bailey is marking spots for corridor lights and putting putty on their boxes.
Moses Mechanical is putting together ducts and installing them in the chases in the suites.
Moses Plumbing is getting everything ready to set tubs and tub valves.
Southland framers came on site around 3:30 pm
1/29/09
Weather: Cold and mostly cloudy. Average temperature in the low 30s.
Sub List:
Bailey Electric
Moses Mechanical
Moses Plumbing
NK Plastering
Southland Framing
Tricon Drywall
Freedom Firepro
Bailey Electric is putting boxes on the 4th floor and wrapping up little incidentals for inspection. Jerime installed the MDP in the mechanical room on the 1st floor.
Moses Plumbing is setting tubs and tub valves and drains and fire caulking all their penetrations on the 4th floor.
Moses Mechanical is setting PTAC sleeves on the 4th floor. They're running duct in the attic for exhaust etc.
Freedom Firepro was here for a little while this morning, but went home because it was too cold to glue pipe.
NK Plastering is mudding over holes and screw heads.
Advanced Wireless is running cable to boxes on the 4th floor.
Southland framing is building fur outs around the exhaust fan duct work in the closets. They're framing the rest of the chase around the VTAC ducts on the 4th floor. They're putting in stair well blocking and hold downs in the sheer walls.
Tricon Drywall is fixing a spot in the 4th floor corridor where there was only one layer of 5/8s rock. They're putting RC channel on the ceiling of the rooms on the 4th floor.
1/30/09
Weather: Mostly cloudy. Highs in the low 50s. Cold this morning and muddy on site.
Sub List:
Bailey Electric
Moses Plumbing
Moses Mechanical
Southland Framing
Tricon Drywall
NK Plastering
Freedom Firepro
Advanced Wireless (data)
Bailey is pulling wires to their Main Distribution Panel (MDP) in the 1st floor mechanical room
Moses Plumbing is finishing the tubs on the 4th floor. They're setting drains and copper.
Moses mechanical is setting PTAC sleeves and readjusting some for the new brick/EIFS design for the exterior.
NK Plastering is spreading mesh and mud on the west side of the building.
I moved Tricon down to the 3rd floor to give the plumbers more space to work on the 4th. They're putting RC channel on the ceilings of the rooms.
Our MEP inspection has been moved to Monday.
John left at 11 am to go to Ft. Smith for a meeting.
I got Magnum Materials to fax over all the invoices for the this job.
2/2/09
Weather: Mostly clear. Highs near 50.
Sub List:
Bailey Electric
Moses Plumbing
Moses Mechanical
Canant Construction
NK Plastering
Advanced Wireless
Canant Construction is pouring concrete in the north parking lot this morning.
Moses Plumbing has their tubs and tub valves in place and they are ready for inspection.
Moses mechanical still has some work to do up in the attic with their duct work. They still have some drains or condensation lines on the 4th floor.
Bailey is ready for inspection on the 4th floor. They are running wires back to the MDP on the 1st.
NK Plastering is spreading color on the front of the building.
The owners and Chase met with John in the office.
2/3/09
Sub List:
Bailey Electric
Moses Plumbing
Moses Mechanical
Southland Framing
NK Plastering
Canant Construction
Tricon Drywall
We had our 4th floor MEP and framing inspection first thing this morning. There were some HVAC and fire suppression issues in the attic and some fire caulking issues with the low voltage and fire alarm people and Freedom Firepro that kep us from passing. Steps are being taken to remedy those problems. Electrical, Plumbing and Framing didn't have any issues.
Bailey is down on 3rd floor joining boxes and pulling wire.
Moses Plumbing is setting tubs on the 3rd floor and getting ready to set tub valves.
Moses Mechanical is finishing their duct work in the attic and putting in the vent for the laundry chute. Elite roofing came today to change out the roof curbs for Moses. Moses' guys dropped their pipe through and capped the curbs.
Canant Construction saw cut the parking lot today.
Tricon Drywall came in and rocked the top of the closets where the exhaust ducts run. They're putting RC channel on the 3rd floor ceilings.
Southland has a few guys here doing 4th floor punch and clean up.
2/4/09
Weather: Mostly clear. Highs in the mid 40s.
Sub List:
Bailey Electric
Moses Plumbing
Moses Mechanical
NK Plastering
Tricon Drywall
Southland Framing
Freedom Firepro.
Bailey is working on the 3rd floor getting ready for 3rd floor inspection next week.
Moses Plumbing is getting the 3rd floor ready for inspection.
John had to leave around 9:30 for a meeting in Searcy. He didn't get back until around 4.
NK Plastering has put the color and window trim on the front section of the building and a lot of the back of the building. They started taking down scaffolding this afternoon.
Southland is cleaning up all the materials off of the 4th floor.
The trusses for the front porch and Porte Corche were delivered this morning.
Tuesday, January 27, 2009
1/20/09 - 1/27/09
![]() |
| From Job # 8.02 / CIS |
1/20/09
Weather: Partly cloudy. Highs in the mid 30s. No chance of rain.
Sub list:
Bailey Electric
Moses Mechanical
Moses Plumbing
Southland Framing
NK Plastering
Freedom Firepro
G and S Insulation
Advanced Sprinkler
Tricon Drywall
I conducted out weekly safety meeting this morning with all trades present.
Jerime with Bailey is putting together the MDP in the mechanical room on the first floor.
Mike with Moses is in Little Rock watching over that job while they pour concrete.
NK Plastering is setting up scaffolding around the building. They’ll start with the foam tomorrow.
Southland’s framers are still working on the extended stay suites. They’re supposed to build part of the fur downs for the VTACs in the suites.
Nick Canant was over here to talk to John and Gary about pouring the north parking lot and the contract on the Searcy job.
Moses Mechanical is setting Ptac sleeves on the 3rd and 4th floor.
We cleaned all the loose material off of the north parking lot in preparation for Canant to pour concrete.
1/21/09
Weather: Cool and mostly clear. Highs in the 40s and windy.
Sub list:
Bailey Electric
Moses Mechanical
Moses Plumbing
Freedom Firepro
Canant Construction
Tricon Drywall
NK Plastering
Southland framing
Bailey electric is running MC cable and setting boxes on the fourth floor. The owners want electrical outlets on either side of the middle steel beam in the meeting room for video projectors.
Moses Mechanical is setting Ptac sleeves and all plenums for Vtacs on the 4th floor and running duct for exhaust fans.
Moses Plumbing is doing their best to get their PVC run to the 4th floor. Mike is saying he’ll be ready for inspection on the 30th.
Tricon is putting pre rock in the meeting room and duct chases in the suites on the 4th floor.
NK Plastering is setting up scaffolding on the front and back of the building to get ready for EIFS
Canant Construction poured part of the sidewalk on the north side of the building. Jerime with Bailey and Todd with Advanced Sprinkler put sleeving under the sidewalk that enters the north side of the building.
Southland framers are working on the 4th floor extended stay suites. They are framing part of the duct chases for the suites. They built one of the walls at the top of the stair well. They need to take out a small wall on the 2nd floor at the north end of the corridor where the ice machine goes.
The owners and Alan and Joey met for about 5 hours.
1/22/09
Weather: Mostly clear. Highs in the 60s.
Sub list:
Bailey Electric
Moses Mechanical
Moses Plumbing
Southland framing
NK Plastering
Freedom Firepro
Tricon Drywall
Canant Construction
City Inspector, Paul Young came by the site today with the state inspector, Tony Woodard. He is having us to add two more access panels in the 4th floor ceiling and 3 way, 4 way light switches to control attic lights. He needs us to make two exterior windows around the pool exhaust area, inoperable. Although he wasn’t entirely happy with some of the design issues, he approved everything that was looked at.
Magnum Materials delivered dry wall for the elevator shaft this morning. They’re storing 25 sheets per floor.
Canant Construction wrecked the forms on the sidewalk they poured yesterday and set more forms in the parking lot.
Southland framers are finishing sheathing and tyveking the exterior of the building. They’re wrapping up the framing in the rooms on the 4th floor and putting dead wood on the ceiling of the poor room for fur downs.
NK Plastering is having to redo scaffolding due to changes on the design of the exterior of the building. They started sticking foam on the back of the building.
Moses Mechanical is installing Ptac and Vtac sleeves and running duct for the bathroom exhaust.
Moses Plumbing is pushing everything through to the 4th floor.
Tricon is finishing pre rock in the duct chases and working on the elevator shaft.
1/23/09
Weather: Partly cloudy. Highs in the 50s
Sub list:
Bailey Electric
Southland framing
NK Plastering
Tricon Drywall
Freedom Firepro
Bailey is getting ready for the 4th floor inspection. They are running low voltage wire for the Ptac thermostats and pulling data and TV cable.
Southland framers are working on 4th floor punch out, building walls at the top of the stairwells and putting up soffet and fascia.
NK Plastering is sticking foam on the front and back of the building.
Freedom Fire is setting sprinkler heads and the heights of their main on the 2nd 3rd and 4th floors. They set the sprinkler heads on the 4th floor 4 different times because the ceiling height changed several different times that day. They were very frustrated.
Tricon drywall is pre rocking the chases in the suites and elevator shaft. They have all of the chases fire taped and ready for the air ducts.
1/26/09
Weather: Cold and cloudy. Highs in the low 30s. 70% chance of freezing rain or sleet.
Sub list:
Bailey electric
Moses Mechanical
Moses Plumbing
Southland Framing
Tricon Drywall
Alan, Chase, Alex, John, and the owners met from 11 am till around 3:30 pm.
Magnum Materials is stocking dry wall in the 3rd and 4th floors.
Moses Plumbing is running PVC through the 4th floor. They’re running Freon lines for the condensing units.
Moses Mechanical is putting ducts together for the 4th floor suites.
Southland framing is putting in blocking in the stairwell and punch out items.
Tricon is rocking the elevator shaft and they’re taping right behind the hangers.
1/27/09
Weather: Cold and wet. Ice and freezing rain fell over night. Anything up off the ground is frozen. Highs in the low 30s. 100% chance of rain, freezing rain, and sleet.
Sub list:
Bailey Electric
Moses Plumbing
Moses Mechanical
Bailey is joining boxes together and preparing for inspection on the 30th.
Moses Mechanical is installing ducts for the suites.
Moses Plumbing is setting tub valves and getting ready to set tubs.
Several trades didn’t show up today due to the weather.
Ken Hacker, an OSHA consultant came to the site today to perform and consultation and walk through. It went really well.
Tuesday, January 20, 2009
1/12/09 - 1/19/09
Weather: Partly Cloudy, Highs in the mid 50s. 10% chance of rain this evening.
Bailey electric is on site. JR asked me abbout room 417. It's been changed from an accesible double queen to a lengthened souble queen and needed to know whether to follow the lay out for the accesible queen, or the regular double queen since we don't have a lay out for a lengthened queen. Chase said to go with the accesible lay out.
Moses Mechanical and Plumbing are on site.
Southalnds framing crew is here installing windows, decking the roof, taking down guard rails and finishing the outside sheathing.
Tricon's drywall creww is putting up pre rock. Nathan is supervising.
Freedom Firepro is on site moving and staging materials.
1/13/09
Weather: Cold and windy. Highs in the mid 30s.
Bailey is on site with a full crew. I got copies of the CCTV placements. They got the sheet rockers to put rock up in the mechanical rooms so they could mount their boxes.
Moses Mechanical and Plumbing is here today. Mike has been in Little Rock the last two days. He'll be back here tomorrow.
Brian is needing cut sheets for the dryer vents so he can stub out for the vent.
Tricon's drywall crew is pre rocking the corriders.
G & S insulation will be back tomorrow to finish the pre rock areas.
Ptac sleeves and wall plenums for the Vtac were delivered today along with drain kits for the Ptac sleeves.
Southland's framers are almost done putting the decking on the roof. Roofers and material will be here tomorrow.
1/14/09
Elite Roofing blacked in the roof with felt paper. They'll be back Saturday and Sunday to finish roofing with shingles.
Southland is putting in windows and working on the floor joists for the second floor extended stay.
Tricon's rockers are putting pre rock in the corridor on all floors.
Freedom Firepro is running PVC and iron pipe on the 1st floor.
Moses Mechanical and Plumbing are on site. Mechanical is running slow. The Plumbers are waiting on the framers to finish to extend stay suites.
Bailey is up on the third and fourth floors running wire and mounting boxes.
1/15/09
Weather: Cold and spitting snow. Highs in the low 30s.
We had a welder come out to look at adjusting some of the steel columns for the front porch.
Southland's framers are tyveking the exterior and putting in windows. They started building dormers for teh rof. They had one dormer set by the end of the day.
Bailey is on site with a full crew working. Jerime is putting up his boxes in the mechanical rooms.
Moses Plumbing and Mechanical is on site. Plumbing is pushing pipe up. Mike was in Little Rock today.
Mechanical is still running condesate lines for the Ptacs and Vtacs.
Freedom firepro is running they're main down the 1st floor corridor.
Canant Construction is setting forms in the North parking lot. Drew was the man in charge. He told methat they were allowing 1" fall from the building to the sidewalk and 1" fall from the side walk to top of curb. I didn't think that was right. I checked the plans and got with Drew about the correct elevations specified i nthe plans. So they are redoing some of their forms.
A fall protection specialist came by at Alex's request so that he and I could ask him some questions about harnesses and tying off.
Gary had the stomach cramps and was out most of the day.
Alex and I pulled measurements and set a string line that is square to the building and at the right dimension for the front porch posts.
1/16/09
Weather: Very cold and windy. Highs in the 20s.
Tony Butler and Pops with Pop's welding showed up to move columns for the front porch. they eneded up moving 12 of the little columns Friday and Saturday.
Southland's framers are building the rest of the dormers for the roof. They set another one and had the other two ready to go up. They're tyveking the outside of the building.
Moses Plumbing is in Little Rock today.
Bailey has their crew on site.
Freedom Firepro has their crew on site.
Alex, Gary and I spent most of the morning laying out the correct dimensions for the steel columns.
I field verified the measurements for the door throats.
1/17/09
Elite roofing came to shingle in the roof today and Sunday.
Southland had some framers setting the last two dormers.
Tony with Pop's Welding was setting the columns for the front porch.
1/19/09
Weather: Cool and windy. Mostly clear. Highs in the upper 40s.
Sub list: Bailey Electric
Moses Mechanical and Plumbing
Southland Framing
Tricon Drywall
Freedom Firepro
NK Plastering
Mike with Moses Plumbing said that he is very frustrated with the framing crew. They'er holding him up by not finishing the extended stay suites and the ADA bathroom that's framed wrong on the 1st floor. He'll be lucky to make the 1/30 deadline for inspection.
Tricon is being slowed down because Alex doesn't have details from Chase about the fir downs in the meeting rooms, Pool room, Breakfast room and Lobby and corridors.
The framers are woking on the extended stay suites on the 2nd, 3rd and 4th floors. They have a lot of work to do.
Mechanical is starting to set a few Ptac sleeves. They have a new guy here names Sean.
The curbs that Moses Mechanical set in the roof are not square at the top. They were manufactered for the wrong pitch. Moses is going to get the right ones out here.
Freedom Firepro is running their trunk in the attic. They have some of their orange lines are in the way of Moses' "p" traps and risers.
Magnum Materials delivered sme dry wall for the pre rockers.
NK Plastering had a couple of guys here to unload a truck of foam.
Bailey is up on the fourth floor running cable and setting boxes.
Nick Canant says if we can get al the materials off of the gravel, he'll pour concrete on Thursday.
I called Hugg and Hall to purchase some propane heaters for the building. They'll have to get them out of Springdale.
Bailey electric is on site. JR asked me abbout room 417. It's been changed from an accesible double queen to a lengthened souble queen and needed to know whether to follow the lay out for the accesible queen, or the regular double queen since we don't have a lay out for a lengthened queen. Chase said to go with the accesible lay out.
Moses Mechanical and Plumbing are on site.
Southalnds framing crew is here installing windows, decking the roof, taking down guard rails and finishing the outside sheathing.
Tricon's drywall creww is putting up pre rock. Nathan is supervising.
Freedom Firepro is on site moving and staging materials.
1/13/09
Weather: Cold and windy. Highs in the mid 30s.
Bailey is on site with a full crew. I got copies of the CCTV placements. They got the sheet rockers to put rock up in the mechanical rooms so they could mount their boxes.
Moses Mechanical and Plumbing is here today. Mike has been in Little Rock the last two days. He'll be back here tomorrow.
Brian is needing cut sheets for the dryer vents so he can stub out for the vent.
Tricon's drywall crew is pre rocking the corriders.
G & S insulation will be back tomorrow to finish the pre rock areas.
Ptac sleeves and wall plenums for the Vtac were delivered today along with drain kits for the Ptac sleeves.
Southland's framers are almost done putting the decking on the roof. Roofers and material will be here tomorrow.
1/14/09
Elite Roofing blacked in the roof with felt paper. They'll be back Saturday and Sunday to finish roofing with shingles.
Southland is putting in windows and working on the floor joists for the second floor extended stay.
Tricon's rockers are putting pre rock in the corridor on all floors.
Freedom Firepro is running PVC and iron pipe on the 1st floor.
Moses Mechanical and Plumbing are on site. Mechanical is running slow. The Plumbers are waiting on the framers to finish to extend stay suites.
Bailey is up on the third and fourth floors running wire and mounting boxes.
1/15/09
Weather: Cold and spitting snow. Highs in the low 30s.
We had a welder come out to look at adjusting some of the steel columns for the front porch.
Southland's framers are tyveking the exterior and putting in windows. They started building dormers for teh rof. They had one dormer set by the end of the day.
Bailey is on site with a full crew working. Jerime is putting up his boxes in the mechanical rooms.
Moses Plumbing and Mechanical is on site. Plumbing is pushing pipe up. Mike was in Little Rock today.
Mechanical is still running condesate lines for the Ptacs and Vtacs.
Freedom firepro is running they're main down the 1st floor corridor.
Canant Construction is setting forms in the North parking lot. Drew was the man in charge. He told methat they were allowing 1" fall from the building to the sidewalk and 1" fall from the side walk to top of curb. I didn't think that was right. I checked the plans and got with Drew about the correct elevations specified i nthe plans. So they are redoing some of their forms.
A fall protection specialist came by at Alex's request so that he and I could ask him some questions about harnesses and tying off.
Gary had the stomach cramps and was out most of the day.
Alex and I pulled measurements and set a string line that is square to the building and at the right dimension for the front porch posts.
1/16/09
Weather: Very cold and windy. Highs in the 20s.
Tony Butler and Pops with Pop's welding showed up to move columns for the front porch. they eneded up moving 12 of the little columns Friday and Saturday.
Southland's framers are building the rest of the dormers for the roof. They set another one and had the other two ready to go up. They're tyveking the outside of the building.
Moses Plumbing is in Little Rock today.
Bailey has their crew on site.
Freedom Firepro has their crew on site.
Alex, Gary and I spent most of the morning laying out the correct dimensions for the steel columns.
I field verified the measurements for the door throats.
1/17/09
Elite roofing came to shingle in the roof today and Sunday.
Southland had some framers setting the last two dormers.
Tony with Pop's Welding was setting the columns for the front porch.
1/19/09
Weather: Cool and windy. Mostly clear. Highs in the upper 40s.
Sub list: Bailey Electric
Moses Mechanical and Plumbing
Southland Framing
Tricon Drywall
Freedom Firepro
NK Plastering
Mike with Moses Plumbing said that he is very frustrated with the framing crew. They'er holding him up by not finishing the extended stay suites and the ADA bathroom that's framed wrong on the 1st floor. He'll be lucky to make the 1/30 deadline for inspection.
Tricon is being slowed down because Alex doesn't have details from Chase about the fir downs in the meeting rooms, Pool room, Breakfast room and Lobby and corridors.
The framers are woking on the extended stay suites on the 2nd, 3rd and 4th floors. They have a lot of work to do.
Mechanical is starting to set a few Ptac sleeves. They have a new guy here names Sean.
The curbs that Moses Mechanical set in the roof are not square at the top. They were manufactered for the wrong pitch. Moses is going to get the right ones out here.
Freedom Firepro is running their trunk in the attic. They have some of their orange lines are in the way of Moses' "p" traps and risers.
Magnum Materials delivered sme dry wall for the pre rockers.
NK Plastering had a couple of guys here to unload a truck of foam.
Bailey is up on the fourth floor running cable and setting boxes.
Nick Canant says if we can get al the materials off of the gravel, he'll pour concrete on Thursday.
I called Hugg and Hall to purchase some propane heaters for the building. They'll have to get them out of Springdale.
Thursday, January 8, 2009
1/7/09
![]() |
| From Job # 8.02 / CIS |
| From Job # 8.02 / CIS |
Trusses for the roof were delivered to the site on 12/30/08 and 12/31/08. The trusses delivered on the 30th were loaded very poorly. One bundle had a metal band strapped to the bundle below it and it broke a top cord. Southland framers worked over the weekend setting the trusses.
1/05/09
Weather: Cold and wet. 100% chance of rain, freezing rain and sleet. Highs in the mid 30s and falling throughout the day.
The 3rd and 4th floor have been icing over and getting dangerous.
Part of Southalnds framing crew was here this morning. Alex got here around noon and Oswaldo was about an hour behind him. The framers started rolling up about 3pm
Bailey's crew has been running home runs and putting temp lights up in the 3rd floor.
Moses Mechanical didn't get here until around noon because of the weather.
Moses Plumbing was here this morning and working all day.
Seaside pools showed up about noon and started working on the whirl pool.
1/6-7/09
Moses Mechanical and Plumbing have been here working. Plumbing is taking their plastic up. They have called in for an above ceiling inspection for the 1st floor. Mechanical is running sheet metal duct for exhaust fans.
Bailey is setting boxes and running home runs where they can. They're fire caulking in the first floor for everything below 8 ft.
Southland is setting piggy back trusses and building the stair case in the lobby.